Tenant Finish Denver CO     Management Team     Project Portfolio     Licenses and Credentials     Subs and Suppliers     Contact Us     Site Map      
Liquid Planet
 
When we started this job we thought that we had plenty of time for the build out as the convention center was going to be quiet for over 5 weeks after Thanksgiving and thru January 7.  The building department had questions on the plans that took about 3 weeks of our scheduled time to resolve.  We were issued a building permit on December 21 and still had the business open for training on January 9. 

 
.